I-69 Taylor Ridge to Plummer Creek : Complete

Greene County, Indiana

Services Performed

Structural Excavation, Pile Driving, Bridge Construction, Box Culverts, MSE Walls

Project Owner

Indiana Department of Transportation

Awards

2016 Indiana Concrete Association – Concrete Achievement Award – Black Ankle Valley Crossing Bridge

Project Overview

The I-69 Taylor Ridge to Plummer Creek project is a $109 million design-build contract with the Indiana Department of Transportation to construct a 2.68 mile section of I-69.  The project, which consists of all new alignment through a remote and environmentally sensitive area, required a pair of bridges with an average height of 60′ to be constructed over the Black Ankle Valley. Extensive ground improvements were completed ranging from high strength fabrics, to wick drains, to staged embankments with chemically modified soils to allow for fills in excess of 100 feet to be made. Millstone Weber’s portion of this project included constructing two Structures approximately 2,000 feet long over the Black Ankle Creek and adjacent wetlands. The original budget for this portion of new I-69 through Central Indiana, south of Bloomington, was $26.2 Million.  The final contract amount was $29.7 Million. The I-69 Taylor Ridge to Plummer Creek project is a $109 million design-build contract with the Indiana Department of Transportation to construct a 2.68 mile section of I-69.  The project, which consists of all new alignment through a remote and environmentally sensitive area, required a pair of bridges with an average height of 60′ to be constructed over the Black Ankle Valley. Extensive ground improvements were completed ranging from high strength fabrics, to wick drains, to staged embankments with chemically modified soils to allow for fills in excess of 100 feet to be made. Millstone Weber’s portion of this project included constructing two Structures approximately 2,000 feet long over the Black Ankle Creek and adjacent wetlands. The original budget for this portion of new I-69 through Central Indiana, south of Bloomington, was $26.2 Million.  The final contract amount was $29.7 Million. Access to the project was limited to a 4.5-mile gravel county road as contracts on each end of the project were not completed. All materials for the project were delivered on the this one county road including 104 concrete beams. The concrete beams were a 153 ft. long and weighed in at 196,000 LBS. The contract was the last one to be awarded on the corridor and was the first one completed.