UPRR HSR Tier 5 : Complete

Alton, IL

Services Performed

Bridges, Earthwork, Drainage, Track Construction, Retaining Walls

Project Owner

UPRR

Project Overview

In 2017, Millstone Weber was contracted by Union Pacific Railroad for the Illinois High-Speed Rail Tier 5 Project. The scope of work included the rehabilitation of two existing structures, one over Wood River Creek which was completed during a seven-day track outage, the other over Cahokia Diverging Canal. MW’s scope also included twenty miles of new fencing, reconstruction of six at-grade road crossings, and installation of ten new jack and bore culverts.